Half the cost is after the forming
A thermoformed part leaves the machine as a shape. It becomes a product through printing, machining, welding, assembly and packing, and on a decorated or assembled part those steps can cost more than the forming did.
The chart on the left splits the added cost. Printing and decoration is 34 percent, assembly 28, machining and drilling 18, welding and bonding 12 and packing 8. Two thirds of it is decoration and assembly, which are also the two steps most often outsourced and least often costed properly.
The right hand panel is the other side: the scrap each step introduces. Machining is 6 percent of parts, welding 4.2, assembly 3.0, printing 1.8 and packing 0.8. Machining introduces more scrap than all the others combined, and it does so at the end of the process where the part is worth the most.
That combination, late and expensive, is why the sequence of secondary operations matters more than the choice of any one of them. A part that is printed and then machined loses the printing when the machining fails.

Printing and decoration
Pad printing is the workhorse for formed parts, because a silicone pad conforms to a curved surface. It handles a logo or a single colour well, it needs a fixture that locates the part positively, and its limit is the depth of the draw: a pad cannot print into a deep recess without distorting.
Screen printing gives a heavier ink film and better opacity, and it needs a flat or gently curved surface. On a formed tray it is usually done on the base or on a flat flange, and the fixture has to hold the part flat without distorting it.
In-mould labelling is the third route and it is not a secondary operation at all: the label goes into the tool and becomes part of the wall. It is worth considering at the design stage, because it removes a whole step and a whole scrap category, and it is impossible to add later without a new tool.
Whatever the method, the fixture is the quality. A printed part that is 0.5 millimetre off register is a reject, and the register is set by how well the fixture locates the part rather than by the printer. A vacuum fixture on a formed part is often not enough, because the part deflects under the pad.
Machining is where parts die
Drilling, milling, routing and punching a formed part all share one problem: the part is thin, it is not flat, and it moves under the cutter. A 6 percent scrap rate on machining is not a tooling problem, it is a fixturing problem, and it is the largest single loss in the secondary sequence.
The first fix is to machine against a feature rather than against an edge. A formed part has moulded features that are accurate to the tool, and locating on one of them is more reliable than locating on a trimmed edge, which is only as accurate as the trim.
The second is to support the cut. A hole drilled in an unsupported wall will tear out on exit, and a backing block or a sacrificial support removes most of that. On a thin wall the support is not optional.
The third is the order. Machining a part before printing means the printing happens on a part that is already known good. Machining after printing means a machining failure destroys the printing as well, and the loss is the full value of the part rather than the value of the cut.
| Operation | Scrap introduced | Main cause |
|---|---|---|
| Machining and drilling | 6.0 percent | Part movement and no backing |
| Welding and bonding | 4.2 percent | Distortion and surface contamination |
| Assemblée | 3.0 percent | Tolerance stack and missing parts |
| Printing and decoration | 1.8 percent | Register and fixture location |
| Packing | 0.8 percent | Handling damage |
Table 1 — What each secondary step costs in parts, and why.
Welding and bonding
Ultrasonic welding suits formed parts that are the same material, and it needs an energy director and a rigid support on both sides. A thin formed wall does not transmit ultrasonic energy well, so the joint is often a moulded rib rather than the wall itself.
Hot plate welding gives a strong joint on large parts and needs the two halves to be held flat against a hot plate. On a formed part with any warp, the plate contact is uneven and the joint is partial, which is a leak that appears in test rather than in production.
Adhesive bonding is the most forgiving and the slowest. Surface energy is the issue: polypropylene and polyethylene need a treatment, PET and PVC usually do not. A bond that fails at month six is usually a surface preparation failure rather than an adhesive failure.
The common thread is that all three depend on the parts being held in a fixture that is stiffer than the parts. A welding fixture that deflects with the part produces a joint that is good in the middle and open at the ends.
Assembly and the tolerance stack
Assembly is 28 percent of the added cost and 3 percent of the scrap, and the scrap is almost always a tolerance stack. Two formed parts that are each within tolerance can fail to assemble if their tolerances are at opposite ends, and the stack has to be calculated before the drawing is released.
The forming tolerance is the largest single contributor, because a thermoformed part is not a moulded one. A draw of 100 millimetres with a wall of 1 millimetre has a thickness variation that translates into a dimensional variation at the base, and the stack has to include it.
The second contributor is the trim. A trimmed edge is located by the trim fixture, so its position relative to a moulded feature carries both the forming tolerance and the trim tolerance, and the two add.
The practical answer is to design the assembly with one adjustable feature: a slot rather than a hole, a rib that can be trimmed, or a snap that takes up a millimetre. A design that needs both parts to be nominal is a design that will have an assembly problem, and the problem will be blamed on the forming.
Planning the sequence
The sequence should put the operations that can fail cheaply first and the ones that add the most value last. Machining before printing, printing before assembly, assembly before packing. That order means a failure costs the least possible at each stage.
The exception is when a later operation needs a feature that an earlier one creates. A hole that is used for location in assembly has to be drilled before assembly, and if the printing also uses that hole, the drilling comes first for a different reason.
The second consideration is work in progress. Every step between forming and packing is inventory, and a part that waits between printing and assembly is a part that can be damaged, contaminated or lost. A short sequence with tight handovers beats a long one with buffers.
The third is the inspection point. There should be one after the operation that introduces the most scrap, which on a formed part is the machining. Inspecting after machining catches the machining failures and the forming failures together, before the printing adds value to a bad part.
| Decision | Do this | Pourquoi |
|---|---|---|
| Machining versus printing order | Machine first | A machining failure costs less before printing |
| Locating a machined hole | Moulded feature, not the trimmed edge | The moulded feature is more accurate |
| Inspection point | After machining | It is the step that introduces the most scrap |
| Assembly design | One adjustable feature | Absorbs the forming and trim tolerance |
| Welding method | Ultrasonic for same material, thin walls | Energy director and rigid support |
| Printing fixture | Positive location, not vacuum alone | The part deflects under the pad |
Table 2 — The sequence decisions, and what each one protects.
What counts as a secondary operation in thermoforming?
Anything after the part is formed and trimmed: printing, machining, welding, assembly and packing. On a decorated part these steps can cost more than the forming.
Which secondary operation causes the most scrap?
Machining, at about 6 percent of parts, which is more than all the others combined. The cause is almost always part movement and a lack of backing rather than the cutter.
Should I print before or after machining?
Machine first. A machining failure then costs the value of the cut rather than the value of the cut plus the printing, and the printing happens on a part that is already known good.
How do I stop a formed part moving during drilling?
Locate on a moulded feature rather than the trimmed edge, and support the wall with a backing block. A thin wall drilled without support will tear out on exit.
Why do two parts in tolerance fail to assemble?
Because the tolerance stack includes the forming tolerance and the trim tolerance, and they add. Design in one adjustable feature so the assembly absorbs the variation.
What is the best welding method for a formed part?
Ultrasonic for the same material and a thin wall, with an energy director and rigid support on both sides. Hot plate suits large parts but needs flat contact, which a warped formed part does not give.
Finished parts, not just formed ones
Tell us the part and what has to happen to it after the trim. We will tell you the sequence, where the scrap will come from, and which step should be designed out.